Check out the inventory of ongoing major projects below to see what is happening in the Township of King!
Transportation Projects
Description of Project
The Gravel Road Conversion Program aims to enhance the existing road network to improve transportation and reduce yearly maintenance expenses by the Township through the resurfacing of existing gravel roads with asphalt paving. Taking a balanced approach, these conversions support King’s commitment to climate change, its objective towards achieving greater fiscal responsibility and cost control and keeps our community safe.
The Work
- The work involves the resurfacing of existing gravel road surfaces with new asphalt paving (base and top course asphalt), culvert replacements, drainage improvements and roadside safety upgrades. Base course asphalt will be placed in 2023, followed by top course asphalt in 2024.
Site Locations
- The following two road segments are included in the 2023 Gravel Road Conversion Program:
- 17th Sideroad from Weston Road to East end
- 18th Sideroad from Jane Street to West end
Disruptions
Access to local residents/businesses will be maintained at all times with a minimum of one lane of through traffic. Access for Emergency Services, Student Transportation Services, Waste Collections and Postal Services will be maintained at all times.
Most Recent Update - September, 2024
- All works have been completed for 18th Sideroad from Jane Street to West end
- Top course asphalt placement has been completed on 17th Sideroad from Weston Road to East end, final driveway transition works are to be completed by September 6th. Topsoil and seed placement to be completed following final driveway transitions.
Expected Timelines / Milestones
- 17th Sideroad to be completed by September 2024, final walkthrough will be completed following this.
Project Manager Contact Information
- Shaquille Cousins – Project Manager -Capital Services – Public Works
- 1 289-252-8134
- Scousins@king.ca
Additional Information
Description of Project
The Road Improvement Program aims to enhance the existing road network to improve transportation within and across the Township. Taking a balanced approach these improvements support King’s commitment to climate change, its objective towards achieving greater fiscal responsibility and cost control and keeps our community safe.
The Work
2024 Road Improvement Program
The work involves road reconstruction or road rehabilitation activities such as pulverizing and paving (base and top course asphalt), localized culvert replacement, drainage improvements and roadside safety upgrades. Base course asphalt will be placed in 2024, followed by top course asphalt in 2025 for Phase 1. Detailed design will be completed for Phase 2 and Phase 3 in 2024.
Site Locations
The following five road segments are to be included in Phase 1:
- Rupke Road
- Hodgson Avenue
- 19th Sideroad (Weston to end of cul-de-sac)
- 16th Sideroad (Weston to Highway 400)
- Station Road (Burton Grove to West Street) design to Metrolinx Permit Application
The following five road segments are to be included in Phase 2:
- Kingsworth Road (from Blueberry Lane to Watch Hill Road)
- Kingsworth Road (from Westgate Circle to Blueberry Lane)
- Kingscross Drive (from Westgate Circle to Manitou Drive)
- Westgate Circle
- Westgate Boulevard
The following two road segments are to be included in Phase 3:
- 16th Sideroad (from Jane Street to Highway 400)
- Magnum Drive
See map of areas under “Additional Information”.
Disruptions
Access for local residents/businesses will be maintained at all times with a minimum of one lane of through traffic. Access for Emergency Services, Student Transportation Services, Waste Collection, and Postal Services will all be maintained at all times.
Most Recent Update - September, 2024
NOTICE - As a part of the 2024 Road Improvements Program, 16th Sideroad, between Weston Road and Highway 400 will be closed from September 30th, 2024, to October 4th, 2024, weather permitting. Please see attached notice and detour plan. Required signage per Book 7 will be erected one week prior to the closure.
2024 Program Updates
- Phase 1 – Construction expected to begin on Hodgson Avenue and 19th Sideroad, Monday September 9th. Construction expected to begin on 16th Sideroad, Tuesday October 15th.
- Phase 2 –The construction scope of work for this phase has been deferred until 2025.
- Phase 3 – Detailed design scope of work has been re-initiated for 2024.
Expected Timelines / Milestones
- 2024 Program Phase 1 – Base course asphalt to be completed on Hodgson Avenue and 19th Sideroad by November 2024
- 2024 Program Phase 2 – Tender package to be ready by 2025
- 2024 Program Phase 3 – Tender package to be ready by 2025
Project Manager Contact Information
- Shaquille Cousins – Project Manager - Capital Services – Public Works
- 1 289-252-8134
- Scousins@king.ca
Additional Information
Description of Project
Kettleby Road - The downtown core along Kettleby Road needs rehabilitation to replace deteriorating infrastructure within the Township's right of way. The Township is planning to reconstruct a 720m segment of Kettleby Road. The limits extend from the Kettleby Bridge on the west side of the Hamlet (just west of #500 Kettleby Road) to the eastern limit of the community, at #270 Kettleby Road. Proposed works for consideration include:
- Adjustments to asphalt platform
- Installation of curb and gutters to improve drainage
- Replacement and/or improvements to existing sidewalks, ditches, culverts and storm sewers
Most Recent Update - September, 2024
Regular updates are posted to the SpeaKing page for this project
Works completed to date:
- 2019 Public Information Centre
- 2022 Public Information Centre
- Topographic survey
- Arborist report
- Stormwater Management report
- Video inspection of storm sewer (to assess current condition)
- Geotechnical investigation (to assess soil and groundwater conditions)
- Cost estimate to bury utilities
- Preliminary design plans
- Permitting from Lake Simcoe Region Conservation Authority
- Confirmation from Department of Fisheries and Oceans (DFO) and Ministry of the Environment, Conservation and Parks (MECP) that project does not require federal or provincial permitting
- Impact assessment of the new road/sidewalk design for each property
- Hydro One utility relocation (moving/replacing poles)
- Vibration monitoring education
In-progress:
- Rogers & Bell to move telecom cables from old poles to new poles
- Hydro One to remove old poles once Rogers/Bell complete
- Forestry contractor to grind down stumps and remove wood debris
- Design of new retaining wall at Kettleby Camp property
- Requests to York Region Police for additional traffic enforcement in the area
- Responding to resident questions, comments and concerns
Upcoming:
- Pre-condition surveys of buildings
- Contractor set up staging area at park
- Contractor to install project signage
Expected Timelines / Milestones
- Vibration pre-condition surveys scheduled for weeks of Sept 9th & 16th
Project Manager Contact Information
- Colin Parks - Project Manager, Public Works
- 905-833-5321 Ext 6568
- cparks@king.ca
Additional Resources
- Kettleby Road PIC Public Notice - December 2022
- Roads
Description of Project
This project will enhance the roads in the Nobleton urban area. These roadways include:
- 15th Sideroad – Highway 27 to 8th Concession (Completed Summer 2022)
- 15th Sideroad – 10th Concession to Highway 27 (Start Spring/Summer 2024)
- 10th Concession – King Road to 15th Sideroad (Start Spring/Summer 2024)
- 8th Concession – 15th Sideroad to King Road (2027)
Most Recent Updates - September, 2024
15th Sideroad – 10th Concession to Highway 27
· Utility company (HydroOne) finalizing pole relocation design. Preparing cost estimate for Township review
10th Concession – King Road to 15th Sideroad
· Hydro One utility pole relocations in progress
· Bell to follow and move cables to new poles
15th Sideroad – Highway 27 to 8th Concession
· Construction substantially complete
· Contractor currently fixing outstanding deficiencies
8th Concession – 15th Sideroad to King Road
· November 2018 - Project Information Centre (PIC) No. 1
· June 2020 - Virtual PIC No. 2
· February 2021 – Schedule ‘B’ Municipal Class EA - Notice of Completion issued
· *NO FURTHER UPDATES UNTIL 2027
Expected Timelines / Milestones
15th Sideroad – 10th Concession to Highway 27
Utility Infrastructure Works (i.e. moving hydro poles) - Q2-Q3 2024
Construction Estimated – Summer 2024
· Start at Highway 27 intersection
10th Concession – King Road to 15th Sideroad
Utility Infrastructure Works (i.e. moving hydro poles) - Q4 2024
Construction Estimated – Spring 2025
15th Sideroad – Highway 27 to 8th Concession
Contractor to fix deficiencies Summer 2024
8th Concession – 15th Sideroad to King Road
Planning and design work to resume in 2027
Project Manager Contact Information
- Colin Parks, Project Manager, Capital Engineering - Public Works
Additional Information
15th Sideroad - Highway 27 to 8th Concession
15th Sideroad - 10th Concession to Highway 27
- Notice of Completion Feb 2021
- Project File Report (PFR)
- Appendix A for PFR
- Appendix B to E for PFR
- Appendix F to H for PFR
- Link to Drawings
10th Concession - King Road to 15th Sideroad
- Notice of Completion Feb 2021
- Project File Report (PFR)
- Appendix A for PFR
- Appendix B to E for PFR
- Appendix F to H for PFR
8th Concession - 15th Sideroad to King Road
Description of Project
Culverts and Bridges are critical Township infrastructure that allows for the safe movement of water over ditches, streams, and rivers – allowing for proper drainage of stormwater downstream into stormwater ponds. Ensuring our bridges and culvert assets are in a good state of repair minimizes transportation and drainage risks to citizens, commuters and the environment at large.
Most Recent Update – August, 2024
- Culvert 336 (Kettleby Road) – Project has entered warranty period, as no more repairs remain to be addressed. Line painting works to be completed in response to pedestrian access inquiries.
- Culvert 310 (11th Concession) – Pre-Construction meeting held with contractor, construction to commence in the September.
- Culvert 326 (Keele Street) – Pre-Construction meeting held with contractor, construction to commence in September.
- Culvert 331 (Kingsworth Road) – Detailed design ongoing.
- Leonard Road Bridge (Leonard Road) – Detailed design has been initiated, in partnership with Town Bradford West Gwillimbury.
Expected Timelines / Milestones
- Culvert 336 (Kettleby Road) – Warranty period to expire May 31st, 2025.
- Culvert 310 (11th Concession) – Construction to begin by mid September 2024.
- Culvert 326 (Keele Street) – Construction to begin by mid September 2024.
- Culvert 211 (11th Concession) - Design has been placed on hold to prioritize Culvert 331 design.
- Bridge 21 (Main Street) - Utility Conflict Plan and relocation meeting to be completed by mid-summer.
- Bridge 22 (Main Street) - Utility Conflict Plan and relocation meeting to be completed by mid-summer.
- Culvert 331 (Kingsworth Road) – Tender ready package to be completed and submitted to Conservation Authority to obtain permit to proceed.
- Leonard Road Bridge – Tender ready package to be completed by end of summer 2024.
Project Manager Contact Information
- Shaquille Cousins– Project Manager, Capital Services– Public Works
- 1 289-252-8134
- Scousins@king.ca
Additional Information
Environmental Projects
Description of Project
Due to aging infrastructure King Township will be replacing the watermains along Bennet Dr.; Forde Cres.; Hollingsworth Dr.; Kingslynn Dr.; and Patton St.. The project has been broken down into two areas, Area 1 and Area 2, please see links below to the maps, showing the extents.
This work also includes:
- Replacement of all water services up to property line and curbstops, under 25mm.
- Installation of additional fire hydrants to ensure fire safety.
- Hardscape and softscape restoration.
We ask all residents to reach out to the Project Manager, if they are aware of any damage caused by the Contractor to buried private infrastructure within the right of way (i.e. irrigation systems, heated driveway systems, etc).
If anyone would like to receive email notifications for project updates, please also reach out to the Project Manager.
Most Recent Update - September, 2024
- Top asphalt placement is completed, which concludes all major works for the project.
- Please reach out to the Project Manager if there are any warranty issues.
Expected Timelines / Milestones
- All works have been completed
Project Manager Contact Information
- Daniel Wilkinson, Environmental Project Manager, Public Works
- 905-833-6572
- dwilkinson@king.ca
Additional Information
Description of Project
King Township will be installing a new diesel back-up generator at the Alex Campbell Sanitary Pumping Station at 76 Alex Campbell Cres.. Back-up power is essential to the operation of pumping stations, to prevent overflows and spills during a power outage.
The work includes the following:
- Installation of new concrete pad
- Installation of new generator
- Installation of generator fencing enclosure
- Electrical works inside and outside of pumping station
- Softscape restoration
Most Recent Update - September, 2024
- The generator concrete pad and fence enclosure have been completed. The remaining electrical works will continue upon the generator delivery, in 2024.
Expected Timelines / Milestones
- Construction is scheduled to start Fall of 2023 and finish Summer of 2024
Project Manager Contact Information
- Daniel Wilkinson, Environmental Project Manager, Public Works
- 905-833-6572
- dwilkinson@king.ca
Description of Project
Due to aging infrastructure, King Township will be replacing the watermains along Lynwood Crescent, Norman Avenue, Elizabeth Drive and Cross Avenue. Please see Project Extents Map, under “Additional Information”, showing the project limits. Please note the extents of the project are subject to change.
This work also includes:
- Replacement of all water services up to property line and curbstops.
- Installation of additional fire hydrants to ensure fire safety.
- Hardscape and softscape restoration.
We ask all residents to reach out to the Project Manager, if they are aware of any buried private infrastructure within the right of way (i.e. irrigation systems, heated driveway systems, etc).
If anyone would like to receive email notifications for project updates, please reach out to the Project Manager.
Most Recent Update - September, 2024
- Investigation works have been completed, the preliminary design is in progress to determine the location of the new watermain, valves, services and hydrants.
- The Township is planning to host a Public Information Centre (PIC) on Wednesday, October 23, 2024, from 6:00pm to 8:00pm at the Nobleton Community Centre (15 Old King Rd., Nobleton) in the Program Room. The PIC will include a brief presentation of the proposed works followed by a Q&A. We encourage everyone to join us.
- Notices will be delivered to all residents.
Expected Timelines / Milestones
- Pre-Engineering investigative works are to take place Spring 2024. Design works are to be completed throughout 2024. Construction is anticipated to start Spring or Summer of 2025.
Project Manager Contact Information
- Daniel Wilkinson, Environmental Project Manager, Public Works
- 905-833-6572
- dwilkinson@king.ca
Additional Information
Facility Projects
Description of Project
- 15th Sideroad & Dufferin Street
- State-of-the-art, high-efficiency, fully accessible Recreation Complex. Key building features include: two NHL-sized ice surfaces, a six-lane 25-metre-long lap pool, a multi-purpose athletic fieldhouse, and a multi-purpose community room.
- The multi-purpose athletic fieldhouse will include an artificial turf field, a three-lane walking/running track, fitness equipment, and a multi-purpose court consisting of basketball, volleyball and pickleball.
Construction of the new Township Wide Recreation Centre, located at 15th Sideroad & Dufferin Street, is well underway – watch this video for a birds-eye view of the progress!
Most Recent Update - September 2024
- As of August 2022, construction began on site and progress is visible. The project continues to move forward with the status of site activities including:
- Exterior Improvements (Asphalt, pavement markings, site accessories, sod, etc.) is on-going and roughly 98% complete
- Interior floor finish is on-going and roughly 98% complete
- Interior framing and associated wall & ceiling finish is on-going and roughly 94% complete
- Aluminum panels & Speciality stone cladding is on-going and roughly 98% complete
- Glazing supply and installation is on-going and roughly 98% complete
- Electrical rough-in of Material, Equipment, fixtures at 96% completion and on-going
- Mechanical rough-in of Plumbing, HVAC, Equipment, Fixtures at 94% completion and on-going
- Rink construction initiated at 96% completion and on-going
- Pool construction initiated at 95% completion and on-going
Expected Timelines / Milestones
- Above ground Mechanical and Electrical rough-in works are on-going and will continue into Q4 2024
- Anticipated occupancy and substantial completion expected for Q4 2024
- Building Utilities have been coordinated with local agencies and will continue into 2024
- Interior block wall, framing, Insulation, and finishes are on-going and will continue into Q4 2024
Project Manager Contact Information
- Brennen Filice
- (647) 234-3975
- bfilice@king.ca
Additional Information
- Progress Photos - February 2024
- Progress Photos - December 2023
- Drone Update - November 2023
- Progress Photos - October 2023
- Progress Photos - August 2023
- Progress Photos - July 2023
- Progress Photos - June 2023
- Progress Photos - May 2023
- Progress Photos - April 2023
- Progress Photos - March 2023
- Progress Photos - February 2023
- Progress Photos - January 2023
- Progress Photos - December 2022
- Progress Photos - November 2022
- Progress Photos - October 2022
- Progress Photos - July 2022
- Photos - Design Concepts
- 2019 Facility Services Master Plan
- TWRC SpeaKING Community Engagement Platform
Description of Project
King Christian Church was constructed in 1851 by the Children of Peace, a Quaker sect. Adapted as a Baptist church in 1931, the building became obsolete in 1978 and was relocated to the site of the King Heritage and Cultural Centre in 1982. The building was designated as a heritage property in 1992 (Township of King By-Law 92-123).
Identified as Canada’s oldest surviving railway station, the King Railway Station was constructed in 1852, and served several different railway companies over more than a century until it became obsolete in 1963. The building has since been relocated twice as part of previous conservation efforts, most recently to the site of the King Heritage and Cultural Centre in 1989, after which it underwent an extensive conservation program. The building was designated as a heritage property shortly after in 1990 (Township of King By-Law 90-80).
The Township of King is committed to the maintenance, protection and enhancement of the heritage resource, and is also dedicated towards facilitating ongoing and new compatible uses for the buildings. Heating and electrical lighting are being installed at both heritage properties, as well as repainting of the interior walls and exterior wood panelling.
The two buildings are located on the property of the King Heritage and Cultural Centre, at 2920 King Road, King City. These structural enhancements will help make the facilities more user-friendly programming and event spaces.
Most Recent Update – September 2024
Construction Progress:
- Removal of existing interior and exterior finishing in progress
- Exposed structural elements to assess the underlying condition
Expected Timelines / Milestones
- Construction initiation: July 2024
- Construction completion: Nov 2024
Project Manager Contact Information
- Randy Wang
- t: 905-833-5321 ext. 4114 | c: 437-424-1418
- Email: rwang@king.ca
Park Projects
Completed Projects 2024
Description of Project
- Tasca Park is an existing 21-acre community park in Nobleton and includes playgrounds, a soccer field, splash-pad, skatepark, toboggan hill, fitness circuit and shade structure. The park is a prominent focal point to the surrounding community and is being implemented over two phases. Phase I was completed in Q1 2016.
- Phase II components include an off-leash dog area, pump track, pickle ball courts, area for ice skating and permanent washroom facilities.
Construction Completed - July 2024
Additional Information
- Contextual Site Plan
- Programmed Areas
- Existing Conditions
- Image Board
- Photo (Potential Phase II Concepts / Amenities)
- Parks & Trails
Completed Projects (2023)
Description of Project
- The Sidewalk Repair Project is related to the replacement of sidewalk and curbs in various locations in King City, Nobleton, and Schomberg within the Township of King.
Project Completed – July 2023
Description of Project
- This redevelopment project will include the replacement of aging play structures and surfaces. The new play area will be fully accessible and incorporate inclusive options, such as a "quiet corner". Additional site amenities include a large picnic shelter with accessible site furnishings, a beach volleyball court, skatepark and paved pathways to connect the park features.
Project Completed - June 2023
Description of Project
This project will see the completion of re-grading works and track upgrades to address safety concerns on Toll Road where it crosses the GO/Metrolinx Railway tracks and connects with Yonge Street (Highway 11). Track upgrades will be completed by GO/Metrolinx with the road work being completed by the Township. Road work scope includes modifying the profile to meet minimum railway grade crossing standards.
Project Completed - November 2023
Additional Resources
Description of Project
- The Sidewalk Repair Project is related to the replacement of sidewalk and curbs in various locations in King City, Nobleton, and Schomberg within the Township of King.
Project Completed - December 2023
Description of Project
- The former Holland Marsh District Christian School, located at 18955 Dufferin St, King, ON, L3Y 4V9, has been closed since 2015. The project involves the complete demolition and removal of all above and underground structures on the property, bringing them to existing grade. The existing church and baseball diamond will retain safe and accessible pathways throughout the construction phase.