Township-Wide Recreation Centre construction update

Posted:
Category
Community Services
General News
Type(s)
News

As of July 2022, construction began on the site of the TownsRec centre updatehip-Wide Recreation Centre and progress is visible. 

The centre will be a state-of-the-art, high-efficiency, fully accessible recreation complex with features that include two NHL-sized ice surfaces, a six-lane 25-metre-long lap pool, a multi-purpose athletic fieldhouse, and a multi-purpose community room. 

The anticipated substantial completion date is expected in the summer of 2024. The project continues to move forward, with the most recent site activities that include: 

  • Site servicing at 50-per-cent completion and ongoing 
  • Building foundation (formwork, reinforcement and concrete) at 50-per-cent completion and ongoing 
  • Weeping tile and sub-slab drainage at 50-per-cent completion and ongoing 
  • Pool basin construction initiated at 35-per-cent completion and ongoing 
  • Structural steel shop drawings (drafting, revisions and approvals) at 30-Rec centre 2per-cent completion and ongoing. 

The short-term look ahead includes substantial site activity, primarily involved with subgrade cast-in-place concrete and reinforcement, mechanical/electrical rough-in and servicing infrastructure.

Upcoming milestones include:

  • The building foundation will continue to progress and is expected to be completed by Q1 of 2023. 
  • Site servicing will continue to progress and is expected to be completed by Q1 of 2023. 
  • Underground mechanical and electrical work are slated to start by Q4 of 2022. 
  • Structural steel submittals continue to be processed with an anticipated delivery to the site slated for Q1 of 2023. 

For more information, please visit king.ca/majorprojects and king.ca/townshipwiderecreationcentre.