Clone of Sanitary Sewer Projects

Nobleton Sanitary Sewer Project

Phase 1 of the Nobleton Sanitary Sewer Project was completed in August 2014, and all property owners are required to connect to the system.  For information about hooking up, or to learn more about the project, please use the links at left. You may also call the hotline at 905-833-4073 with enquiries or email nobletonsewers@king.ca

Important Facts for Property Owners

  • Property owners are required to connect to the system within one year of its installation in their neighbourhood and pay a charge to the Township for construction costs.
  • Property owners are also responsible for the cost of getting the work done to install the sewer pipe on their property and decommission the septic system. This cost varies from property to property.
  • Installing the connection pipe on your property requires a Building permit and Township inspection to ensure the system is constructed properly.
  • Sewer usage billing begins once your connection is made, but even if you haven’t hooked up, once the 12-month deadline has passed, you will be charged the sewer usage fee.
  • Property owners have paid or are already paying (through taxes) for the capital construction costs.

King City Sewer Project

The Township of King installed sewer systems in King City beginning in 2006 and completed most* of the construction in summer 2011 when the sewers in Contract Area 5 became available for hook up.

Although most property owners have hooked up to the system, some still need to do so (see map for the compliance rate by Contract Area) in our June 2012 newsletter.

Once property owners have connected to the system, it’s important to advise the Township so that the work can be inspected and your property cleared for by-law (2007-110) compliance. Property owners should be aware that the longer they wait past the 12-month deadline, the greater likelihood there is of increased costs when they hook up.

As part of the final restoration work following the sewer construction, asphalt is being placed in all Contract Areas over the next two to three years. This work is funded with federal and provincial government support.

For more information about the King City sewer project, please contact:

Wayne Pinkney C.E.T., Project Manager
905-833-4575
wpinkney@king.ca